Mechanical Completion, Hook-Up & Commissioning - Get it done right first time
Every day there are electrical failures of plant, for various reasons. In some cases, the failure could have been avoided; in other cases, it could not be avoided. When a failure occurs, it can result in loss of service, equipment damage or even harm to personnel. On the assumption that the engineering design is correct, we must strive to ensure the installation, hook up and commissioning are also done correctly. In many cases, extensive equipment damage can result if installation and commissioning are done incorrectly. This adds to a greater repair time and longer loss of service.
Basic Roadmap to Commissioning
Develop a Commissioning Plan including a PERT diagram (sequence plan).
Develop a Systemization Procedure
Develop and populate the Mechanical Completions and Commissioning Database with System and Subsystem data and respective Inspection and Test Record (ITR) Identifiers.
Systemize main electrical drawings, such as one line diagrams
Develop / review / revise Mechanical Completion Check Sheets and Inspection and Test Records (ITRs)
Develop System and Subsystem folders according to the systemization principles.
Host MC and Commissioning meetings to communicate the process to all stakeholders.
Develop and maintain Punch Lists, comprising A, B and C punch items.
Assemble Mechanical Completion dossiers and MC Acceptance Certificates
Assemble Commissioning Completion dossiers and Commissioning Acceptance Certificates
Manage the Client Sign off of Final Acceptance Certificates.
Commissioning Sequence Diagram
Systemization of One Line Diagram
Mechanical Completion refers to the installation and hookup. These tasks are often done by different groups.
Mechanical Completion
We monitor, verify and support:
Equipment and bulk materials have been installed according to the approved drawings and meet the specifications
Oversee the work performed by inspectors, to confirm Mechanical Completion Check Sheets are completed correctly
Review of Punch Lists to verify status of A/B and C punch items are accurate and complete
Assist in the management of Punch List Register to close all punch items before next phase.
Support / witness special tests before dressing out cables and hookup
Hook-Up
We monitor, verify and support:
All hookup work is performed correctly
All inspections and tests are completed and satisfactory (see above)
Ensure that the work is ready for the next phase of commissioning
Commissioning
We monitor, verify and support:
Planning of test schedule identifying key activities for temporary equipment and personnel
Preparation of system for commissioning and management of all notifications including customer/surveyor.
Logistic support towards and installation of, all temporary equipment required to support commissioning of the system.
Bringing up systems in a safe and coordinated manner
Ensuring all documentation is available to record the process and to sign off.